HIGH COURT OF ANDHRA PRADESH
THE HONOURABLE CHIEF JUSTICE DEVINDER
GUPTA & THE HONOURABLE MR. JUSTICE C.V. RAMULU
Writ Petition No.17803 of 2004, W.P.M.P.Nos.23349 of
2004, 24319 of 2004, 24421 of 2004, 25636 of 2004, 24313 of 2004, 24383 of 2004,
24612 of 2004, 25780 of 2004, 26061 of 2004.
Vedire Venkata Reddy & Others Versus
Union of India & Others
JUDGMENT
Common Order: (Devinder Gupta, C.J.)
Petitioners, including a retired Engineer-in-Chief, A.P. TRANSCO, belong to
various sections of society. Petitioners 3 to 6 and others are stated to have
formed an association called “Pulichintala Project Porata Sambhavana
Committee”. They claim that this association includes the affected farmers of
Guntur and Nalgonda Districts whose agricultural lands are situate near the
proposed site of Pulichintala Project and to safeguard the interests of the
people living in twelve villages situated in Nalgonda and Guntur Districts,
whose lands are likely to be submerged if the Project is allowed to commence
at the site, this writ petition has been filed as ‘Public Interest Litigation’
on 30.9.2004. The writ petition challenges the action of the respondents in
commencing the Pulichintala Project for the purpose of stabilizing the command
area under Prakasham barrage. Inter alia, it is alleged that the respondents
have decided to commence the Pulichintala Project without obtaining
environmental clearance, as envisaged under the Environment (Protection) Act,
1986. Without obtaining such consent, the petitioners allege that the work of
the proposed project cannot be commenced.
2. Rule nisi was issued in the writ petition on 4.10.2004. The petitioners
also filed miscellaneous application, viz., W.P.M.P.No.23349 of 2004, praying
for issuance of directions that the respondents be restrained from finalizing
the tender process and not to commence the construction work of the project
during the pendency of the writ petition. Time was sought to file counter
affidavit and reply to the miscellaneous application. In the meanwhile,
apprehending likelihood of passing some interim orders a number of
miscellaneous applications have been filed by some individuals and
associations for being impleaded as party respondents to the writ petition and
to permit them to submit their views before the Court. The said applications
were also taken up for consideration. In view of the averments made in the
implead applications, they are orders.
3. The main relief sought by the petitioners in the writ petition is to
declare the action of the respondents in taking steps to commence the
construction work of the Pulichintala Project without obtaining environmental
clearance from the Central Government as arbitrary, illegal and violative of
principle of natural justice and contrary to the notification dated 27.1.1994
issued by the first respondent. The second relief sought in the petition is to
direct the respondents to shift and relocate the Pulichintala Project to an
alternate location immediately after the confluence of Muneru Tributary.
4. When we commenced hearing, learned counsel for the parties were asked to
address us only on the question of grant of an interim relief, if any, as
prayed for by the petitioners on the ground that environmental clearance has
not been obtained. On the other aspects raised in the petition, we pointed out
that the said questions would arise for consideration only after this question
is answered. Learned Counsel for the respondents pointed out that since
elaborate arguments on the points of environmental clearance have been
addressed, the writ petition itself can be disposed of.
5. Submissions were made on the question that whether or not it is obligatory
on the part of the State Government to obtain environment clearance prior to
commencement of the project work in any manner whatsoever or whether the work
undertaken is such which would not require the said clearance. Arguments were
also addressed on behalf of the State Government that though it was bound to
obtain necessary environmental clearance before the commencement of the work
but by entrusting the construction work to M/s. Srinivasa Construction Company
after evaluation of the tenders and acceptance thereof, the only work
undertaken at the site is only to assess soil strata which is a part of
foundation investigation along with dam access so as to assess the soil
parameters for finalization of detailed designs for the foundation of the dam.
It was urged that the construction of Pulichintala Project will involve
investigation work for assessing the soil parameters for the purpose of
preparation and finalization of designs, drawings, etc., which form part of
foundation investigation as per Central Water Commissioner Guidelines, 1983.
The contractor has to undertake the said exercise under the present E.P.C.,
turn key system, who had in fact undertaken work only for the purpose of
foundation investigation to enable him to finalize the design which would not
come within the purview of the actual commencement of construction work of the
project. The investigation and preparation of designs itself will take about
six months time. In this backdrop, learned counsel for the respondents and the
other impleaded respondents pointed out that there should not be any restraint
on the respondents in going ahead with the work and there should not be any
injunction of any kind particularly considering that it was a major
multipurpose project for which clearance had already been issued by the
Central Water Commission. Moreover considering the larger public interests and
the persons likely to be benefited by the project, any restraint, if imposed,
is likely to adversely affect the beneficiaries and will not be in public
interest.
6. Some of the impugned respondents also questioned the very locus standi of
the petitioners to file such a petition as public interest litigation saying
that the petition is not at all in public interest but is contrary to the
larger interests of majority of the citizens of the State. Another objection
is about the jurisdiction of the Court to entertain such a petition on the
ground that water disputes between the Governments of Karnataka, Maharashtra
and Andhra Pradesh, including the Pulichintala Project, h have already been
referred to Krishna Water Dispute Tribunal, which Tribunal alone can agitate
these water disputes under Section 5 of the Inter-State Water Disputes Act,
1956 and in view prohibition contained in Article 262(2) of the Constitution
read with Section 11 of the Inter-State Water Disputes Act, 1956, this Court
shall not exercise jurisdiction in respect of water dispute.
7. The petitioners alleged that as per the proposal of the State Government,
Pulichintala Project is proposed to be located before the confluence of Muneru
tributary resulting inflow of water from Muneru into Krishna River and
thereafter into Bay of Bengal. Since the capacity of Krishna barrage is only 4
t.m.c., In recent times a number of protests were received from general public
with regard to location of Pulichintala Project and a report was also
submitted by Engineer, T. Hanumantha Rao, the then Chairman Technical
Committee, Water Conservation Mission, Government of Andhra Pradesh called
“Technical Alternatives to Pulichintala Project”. The report had pointed out
that the site selected was not a suitable or beneficial site. Apart from other
disadvantages, the proposed project has not received any environmental
clearance from the Central Government i.e., the Ministry of Environment and
Forests, which is mandatory. The petitioners highlighted the fact that under
the Notification issued on 27.1.1994, there is a procedure laid down in
obtaining environmental clearance. The State Government is the Project
Authority and has to apply for clearance. It has also to append along with its
application, the proceedings of public hearing, which is also mandatory under
the relevant provisions. On an earlier occasion when the fourth respondent had
commenced the construction work of the project without conducting any public
hearing and without obtaining consent, Writ Petition No.15425 of 2001 was
filed. The State Government had pointed out that it had already taken steps to
obtain environmental clearance. The Writ Petition filed at that stage
questioning the implementation of the project at the given site was held to be
premature and was disposed of by a Division Bench of this Court on 12.9.2001
observing that obtaining permission from the Central Government was mandatory.
The petitioners, thus, alleged that the respondents are now proceeding ahead
in commencement of the work without obtaining environmental clearance.
8. The stand of the State Government on the environmental clearance is that
the Government after considering the importance of the project had submitted a
proposal to the Central Water Commission on 16.1.1996 for its approval. The
Central Water Commission in its 64th meeting in Advisory Committee of
Irrigation Flood Control and Multipurpose Project held on 3.4.1996 decided to
recommend the Pulichintala Project as a techno economic viable project subject
to obtaining environmental clearance. After the recommendation of the Central
Water Commissioner, detailed investigation and survey has been undertaken by
the fourth respondent. For the purpose of obtaining environmental clearance,
as prescribed under the Environmental Impact Assessment Notification, 1994,
steps for conducting public hearing have been taken by the State Government,
as suggested by the Pollution Control Board. Public hearing was sought to be
conducted on 23.3.1998 but the same could not be completed due to strong
resistance from various groups, political parties and voluntary organization.
When the matter stood thus, the inflow of water into Krishna River has
drastically been reduced due to construction of various dams at the upstream
of the Krishna River in Karnataka State and due to prevailing drought
conditions in the State. There is dire necessary to proceed ahead with the
Pulichintala Project for regulating the water release to Krishna delta as well
as to meet the increased demand of power. In this view of the matter, the
Government has decided to immediately take up the construction of the
Pulichintala Project and accordingly tenders were invited on 23.2.2000 for
construction of non overflow dam and spill way across the river Krishna on
E.P.C., turn key system. After evaluation, tenders were accepted and the work
was entrusted to the contractor. As regards public hearing, it is stated that
it is now scheduled to be held on 10.11.2004 at 10 AM., at Mandal Revenue
Office, Mallacheruvu, Nalgonda District and all necessary steps as required
under Schedule IV of the Environmental Impact Assessment Notification, 1994
have been taken. It is also stated that the entire effort of the State is to
save time and the action of the State Government in award of contract cannot
be found fault with.
9. It is not disputed by the State Government that obtaining environmental
clearance is mandatory before commencement of construction work. In the
affidavit of the Project Administrator and the Superintending Engineer, it is
also stated that assuming that the project is allowed to proceed, it is only
when the construction of the dam up to bank level is complete, the lands will
be submerged and it is expected to take at least one and half year and till
then no land will be subjected to any submersion. As such there cannot be any
interjection with the present work being undertaken. Further, it is stated
that in view of the importance of the project and for economic development of
the State all efforts are being made by the State Government for early
completion of the project for which no exception can be taken by any person.
As noticed above, it has not been disputed by respondents 1 to 4 that some
work is going on at the site, which according to the Project Administrator is
only an investigation work for assessing soil parameters for the purpose of
finalizing the designs and drawings and the said construction will not come
under the purview of the environmental aspect and does not require any prior
permission of the Ministry of Environment and Forests, Government of India.
10. We need not take note of the State Government’s stand on the merits at
this stage since on merits of the project, the petition is still premature.
The only question, at this stage, is that whether the State Government can
proceed ahead with implementation of project without environmental clearance.
11. On behalf of the Central Government though no counter affidavit has been
filed so far, but learned Standing Counsel for the Central Government has
handed over to us a communication received by him from the Additional
Director, Ministry of Environment and Forests, Government of India dated
26.10.2004, which states that the Irrigation and Command Area Development
Department, Government of Andhra Pradesh has on 20.10.2004 submitted its
proposal in respect of Pulichintala major irrigation project in Guntur
District for site clearance. The letter further states that the proposal is
under examination and after the site clearance is granted, the project
authorities are required to submit comprehensive environmental impact
assessment report incorporating the suggestions given in the public hearing
for environmental clearance. Learned Advocate General pointed out that it is
only a communication from the Ministry of Environment and Forest to its
counsel and is not a counter affidavit, therefore, no cognizance of the same
can be taken since the State Government has no occasion yet to verify the
facts as to whether site clearance had or had not been granted. In any case we
are taking the stand of the 1st respondent on record since specifically the
Additional Director requested the Standing Counsel for Central Government to
bring this fact to the notice of the Court.
12. The locus standi of the petitioners has been challenged by making
reference to the cause title of the order passed in earlier Writ Petition
No.15425 of 2001 decided on 12.9.2001 (Professor K. Purushotham Reddy and
another v. State of Andhra Pradesh and Others). The said writ petition was
filed when some work at the project site was commenced. The writ petition was
dismissed as premature since environmental clearance, which is required to be
obtained had not been obtained and the State Government had pointed out that
it was taking steps to obtain environmental clearance. Mr. S. Ramachandra Rao
referred to Annexure-K appended to the present petition. It is a copy of
representation sent by Telangana Congress Party addressed to the Governor of
the State on the Pulichintala Project. It was pointed out that in the earlier
writ petition Professor K. Purushotham Reddy, the working President was the
petitioner whereas its Treasurer, P. Murali Manohar Rao, is one of the
petitioners in the present writ petition and therefore it is a mala fide
petition. Considering the nature of allegations made in this petition, the
mere fact that one of the petitioners is an office bearer of a particular
party, whose office bearer was petitioner in the earlier petition will not be
a ground to hold that the petition is mala fide or that the petitioners have
no locus standi to the file the petition. The petitioners are public spirited
persons and form part of a homogenous group likely to be adversely affected in
the event of the project being set up at the site in question. They have
highlighted and tried to project the grievance of the landowners that the
State Government is proceeding with the work contrary to the procedure laid
down in law. Even as per the affidavit of the State Government, there had been
strong resistance from various groups, political parties and voluntary
organizations due to which the requisite public hearing, which earlier was
sought to be conducted on 28.3.1998, could not take place. We do not find any
force in such like submission that it is not a petition filed in public
interest and turn down this objection. Considering the nature of the points
raised and the importance of the project, it cannot be said that it is a
motivated mala fide petition not filed in public interest.
13. Public Interest Litigation is that where the public in general are
interested in vindication of some rights or enforcement of some public duty.
Such litigation has hitherto been entertained by the Supreme Court under
Article 32 and by the High Courts under Article 226 of the Constitution not
only from associations or organizations or individuals interested in a common
cause. Where public interest is undermined by arbitrary or perverse executive
action, it is rather duty of the High Court to issue appropriate writ. We may
make reference to Chaitanya Kumar v. State of Karnataka (AIR 1986 SC 825). In
view of a spate of petitions filed as Public Interest Litigation, latterly it
has been held that before entertaining a letter or communication as PIL, the
Courts should take adequate care and caution that the process of the Court is
not abused or misused. In doing so the Court should be prima facie satisfied
that the information laid before the Court is of such a nature, which call for
judicial scrutiny. Where the Court is so prima facie satisfied it may proceed
to investigate into the allegations with a view to meeting out justice. In
exercising the power of entertaining PIL, the Court should not forget the
object with which procedural technicalities in such like petitions have been
relaxed e.g. to provide easy access to justice to weaker section of the
community and to combat exploitation and injustice and to secure to the
under-privileged segments of society their social and economical entitlement.
Such procedural technicalities are also relaxed in petitions filed to redress
public injury, enforce public duty, protect social rights, vindicate public
interest and rule of law, effect access to justice to economical weaker class
and meaningful realization of fundamental rights. It has been held in M/s. J.
Mohapatra and Co. v. State of Orissa (AIR 1984 SC 1572) that once the Court is
satisfied as to the public mischief to be remedied, it would not insist on the
locus standi of the petitioners. A balance has to be struck by the Court in a
public interest litigation between two conflicting interests i.e., (i) no body
should be indulged in wild and reckless allegations besmirching the character
of others and (ii) avoidance of public mischief and to prevent publicly
mischievous executive action as held in Chaitanya Kumar case (1 supra). Where
public mischief is predominant, the Court may not only restrain executive
action but may also give appropriate affirmative action. (See: State of H.P.,
v. Umed Ram Sharma (AIR 1986 SC 847)).
14. On the maintainability of the writ petition on the ground that it is filed
in representative capacity and must be dismissed since leave of the court has
not been obtained under Order 1 Rule 8 of the Code of Civil Procedure,
reliance was placed on a judgment of the Supreme Court reported as Ramchander
Sunda v. Union of India ((1999) 9 SCC 105). The objection is ill-founded
inasmuch the writ petitioners have no where stated that the writ petition is
being filed in representative capacity or that they are seeking leave of the
Court under Order 1 Rule 8 of the Code of Civil Procedure. The petition has
been filed in public interest and on the parameters as noticed above and as
laid down by the Supreme Court in Narmada Bachao Andolan v. Union of India
((2000) 10 SCC 664), such a petition filed in public interest undoubtedly
would be maintainable. We may also observed that in view of Section 141 of the
Code of Civil Procedure, even provisions of Order I Rule 8 are not applicable
to a petition filed under Article 226 of the Constitution of India. We hold
that the petition has been filed bona fide and is in public interest.
15. Now the objection was raised about jurisdiction of the Court to entertain
and decide this writ petition. As a limb of that objection reference was made
to the decision of the Supreme Court in State of Karnataka v. State of A.P.,
and Others ((2000) 9 SCC 572). Two Civil Suits (O.S.No.1 of 1997 and O.S.No.2
of 1997) were decided by the Supreme Court. State of Karnataka had filed suit,
O.S.No.1 of 1997 before the Supreme Court under Article 131 of the
Constitution of India, inter alia, praying for an injunction restraining the
State of Andhra Pradesh from executing several projects, including
Pulichintala Project. State of Maharashtra, defendant No.2 in the said suit,
agreed with the State of Karnataka regarding apportioning of water of river
Krishna for constructing various projects like Pulichintala. One of the issues
(issue No.11) in the said suit was whether the decision of Krishna Water
Dispute Tribunal entitled the State of Andhra Pradesh to execute projects,
including Pulichintala. The Apex Court, in the context of the prayer made in
the plaint and in view of the findings, held that the question of granting
relief sought for by the State of Karnataka did not arise, which relief
included an order of injunction restraining the State of Andhra Pradesh from
executing several projects, including Pulichintala. The Supreme Court,
however, observed that in the event of any riparian States approaching the
Central Government, it would do well to constitute a tribunal, which tribunal
would go into the entire disputes. It was pointed out that now a Tribunal has
since been constituted. It was, thus, urged that the relief sought for in the
O.S.No.1 of 1997 before the Supreme Court was similar to the relief now sought
in this petition, which was turned down by the apex court, therefore, this
court ought not to exercise its jurisdiction under Article 226 of the
Constitution in favour of the petitioners and would decline to grant the
relief.
16. Such an objection raised on behalf of the respondents has to be simply
turned down on the ground that the present writ petition is neither a petition
filed by any of the riparian States, nor by the agents or by a person claiming
rights through the riparian States. Filing of the suit by the State of
Karnataka and raising an issue by State of Maharashtra in the Apex Court
cannot affect the rights of persons, like the petitioners, who belong to State
of Andhra Pradesh, in approaching the Court where the questions raised are not
such which were before the Supreme Court in O.S.No.1 of 1997 or could be
raised in the said suit. The cause of action is also not the same.
17. Another limb of the same objection is that the writ petition has raised a
dispute relating to water, therefore, in view of Article 262(2) of the
Constitution of India read with Section 11 of the Inter-State Water Disputes
Act, 1956 jurisdiction of the Court is barred. Reference in that behalf was
placed on the decisions of the Supreme Court in Tamilnadu C.N.V.V.N.U.P.
Sangam v. Union of India (AIR 1990 SC 1316=(1990) 3 SCC 440), State of
Tamilnadu v. State of Karnataka ((1991) Suppl.1 SCC 240), and Re: Cauvery
Water Disputes Tribunal ((1993) Suppl.1 SCC 96). No doubt the writ petition
would not be maintainable provided a water dispute as defined in Inter-State
Water Dispute Act, 1956 is raised therein. Whether such a dispute is raised in
the writ petition is the question to be answered.
18. ‘Water dispute’ has been defined in Section 2(c) of the Inter-State Water
Dispute Act to mean any dispute or difference between two or more State
Governments in respect to the use, distribution or control of waters of or in
any inter State river or river valley. It was urged that Krishna River Water
Dispute Tribunal award popularly known as Bachwath award in Chapter III made
it clear that River Krishna, which flows from Maharashtra, Karnataka and then
Andhra Pradesh is an inter State river and the words “use”, “distribution” or
“control” in Section 2(c)(i) of the said Act are of wide import and would
include regulation and development of waters and waters of any inter State
river which can only be regulated through construction of reservoirs and dams,
etc. Since the proposed Pulichintala Project is a balancing reservoir with the
aim of use, distribution or control of water of river Krishna, which is inter
State River, such a dispute would be covered within the definition of ‘water
dispute’ as defined in Section 2(c) of the Act thereby ousting jurisdiction of
this Court. It was urged that it is not necessary that such a dispute must be
raised only inter se States. Even if certain individuals would approach this
Court, instead of another State Government, it would not confer jurisdiction
on this Court to entertain a dispute which is a “water dispute”. Article 131
of the Constitution confers original jurisdiction on the Supreme Court to
adjudicate upon disputes between the Government of India and one or more
States or between two or more States and Article 262(2) of the Constitution
read with Section 11 of the Inter-State Water Disputes Act bars jurisdiction
of any Court from entertaining any “water dispute” as defined in the said Act.
Reliance was also placed on the decision of Gujarat High Court in Babubhai
Jashbhai Patel v. Union of India (AIR 1983 Gujarat 1) stating that invoking
jurisdiction of the Court by the petitioners in this court is misconceived.
19. We have given due consideration to the objection raised and find no force
in such submissions that the writ petition raised a dispute which is “water
dispute” and for that this court has no jurisdiction to entertain the writ
petition. Article 262 refers to disputes relating to waters and envisage
adjudication of disputes relating to waters of Inter State rivers or river
valleys by a Special Tribunal. It says that Parliament by law may provide for
adjudication of any dispute or complaint with respect to the use, distribution
or control over the waters of, or in, any inter State river or river valley
and also provide for barring jurisdiction of the Supreme Court and other
Courts that notwithstanding anything contained in this Constitution,
Parliament may by law provide that neither the Supreme Court nor any other
Court shall exercise jurisdiction in respect of such dispute or complaint in
case such a law is brought into force. The Parliament in exercise of its power
has enacted Inter-State Water Disputes Act, 1956, being a legislation to
provide for adjudication of disputes relating to waters of Inter State Rivers
and River valleys. ‘Water dispute’ in Section 2 (c) is defined as under:
“any dispute or difference between two or more State Governments with respect
to -
(i) the use, distribution or control of the waters of, or in, any inter-State
river or river valley; or
(ii) the interpretation of the terms of any agreement relating to the use,
distribution or control of such waters or the implementation of such
agreement; or
(iii) the levy of any water-rate in contravention of the prohibition contained
in Section 7.”
20. Section 11 of the Act bars the jurisdiction of the Supreme Court and other
courts saying:
“Notwithstanding anything contained in any other law, neither the Supreme
Court nor any other Court shall have or exercise jurisdiction in respect of
any water dispute which may be referred to a Tribunal under this Act.”
21. A dispute would come within the definition of ‘water dispute’ if it is
between two or more governments, which is a sine qua non and therefore the
very requirement of the definition is not met. The argument on behalf of the
respondents that what cannot be done directly cannot be permitted to be done
indirectly and therefore the reliefs which the petitioners have sought were
the reliefs before the Supreme Court or could have been raised by other
States. Instead of the riparian States coming forward, certain individuals in
the garb of a PIL have approached this Court to stall the implementation of
the project. It was thus urged that any dispute which would have the effect of
stalling a project of the nature which is being envisaged for use,
distribution or control of the waters of an Inter-State River would not be
entertainable by any Court.
22. In no part of the writ petition, there is any indication or averment that
the dispute raised is about the use, distribution or control of the water of
Krishna River arising between States. Andhra Pradesh is the last beneficiary
State of Krishna waters after the States of Karnataka and Maharashtra.
Whatever beneficial uses the State of Andhra Pradesh can make use of the
Krishna River, it is by implementation of one of such projects which is the
subject matter of the present petition. It has been filed by certain
individuals representing one section of the society urging that though there
cannot be any dispute in the implementation of the project but it cannot be
constructed at the proposed site for various reasons or in any case in the
absence of any environmental clearance under the provisions of the Environment
(Protection) Act, work cannot be commenced. Other points have also been raised
in the suit that for various reasons, how and in what manner project ought to
be implemented. Dispute would not by any stretch of imagination fall with the
definition ‘water dispute’ thereby ousting the jurisdiction of the Court.
Before the Division Bench of Gujarat High Court, writ petition had been filed
by Babubhai Jashubhai Patel etc., private citizens by way of public interest
litigation, since they felt that royalty paid to the State for crude oil
produced in the State was extremely low and therefore they had sought quashing
of a notification to be illegal. The High Court in that case that in view of
Article 131 of the Constitution such a petition cannot be entertained in High
Court. Such a dispute could be raised only in Supreme Court. The judgment is
not application to the instant case. It cannot be said that either State of
Maharashtra or Karnataka could have raised such a dispute objecting to the
location of the site of the project. Petition is filed by the residents of
Andhra Pradesh projecting the cause of the owners of the land likely to be
adversely affected by the implementation of the project. Such a grievance can
only be made by or on behalf of the person interested and not by any of the
riparian States. Therefore, neither the bar contained in Section 11 of the
Inter-State Water Disputes Act or Article 262 of the Constitution would apply
nor Article 131 of the constitution has any relevance and for that reason the
objection of the respondents is unsustainable.
23. The question, thus, remains to be decided is about environmental
clearance. As we have noticed above, it is not the stand of the State
Government that environmental clearance is not necessary before commencement
of the construction of the project. In any case, we would make reference on
this point also to the decision in State of Karnataka v. State of A.P., (6
supra). Two original suits were decided by the Supreme Court – one filed by
the State of Karnataka (O.S.No.1 of 1997) and the other by the State of Andhra
Pradesh (O.S.No.2 of 1997). In the suit filed by the State of Andhra Pradesh,
O.S.No.2 of 1997, issue No.15 was whether Upper Krishna State II Multipurpose
Project could be executed without obtaining the environmental clearance under
the Environment (Protection) Act, 1986 and the notification issued by the
Central Government in 1994 in exercise of its powers under the said Act and
the rules made thereunder, which mandatory requires various analysis,
including dam break analysis. Onus of this issue was thus placed on the State
of Andhra Pradesh. State of Andhra Pradesh had sought number of reliefs in the
suit, but essentially the reliefs related to the construction of Almatti Dam
by the State of Karnataka. Issue No.15 had been framed on the plea raised by
the State of Andhra Pradesh that the State of Karnataka was likely to execute
Upper Krishna Stage II Multipurpose Project without getting environmental
clearance under the Environment (Protection) Act under the notification issued
by the Central Government in exercise of powers under the same Act and the
Rules made thereunder.
24. The apex court held that under Article 256 of the Constitution, it is an
obligation for the States to exercise their power ensuring compliance with the
laws made by parliament and even it enables the Union Government to give such
direction to the State, as may be necessary for that purpose. It was further
held that every such project, whether being executed in the State of
Maharashtra or Karnataka or Andhra Pradesh, must be approved by the
appropriate authority of the Government of India and necessarily, therefore,
before any approval is accorded, the project must be found to have complied
with all the relevant laws dealing with the matter. Since before the Supreme
Court no material was placed that the State of Karnataka had carried out any
project in contravention of the provisions of any particular law made by
Parliament or in contravention of any direction issued by the Government of
India, the issue was held to be premature. But the Supreme Court laid emphasis
that all the projects of the different States concerning user of water
available to them in respect of an Inter-State river must be duly sanctioned
by the appropriate authorities of the Government of India after proper
scanning and it is only then the State would be entitled to carry out the
same. In this view of the matter also, we are of the view that it will be
totally impermissible for the State of Andhra Pradesh to proceed ahead in
implementing the project without getting appropriate clearance as is envisaged
under the Environment (Protection) Act, 1986.
25. Section 3 of the Environment (Protection) Act, 1986 authorizes the Central
Government to take all such measures as it deems necessary or expedient for
the purpose of protecting and improving the quality of the environment and
preventing, controlling and abating environmental pollution. Sub-section (2)
says that in particular and without prejudice to the generality of the
provisions of sub-section (1) such measures may include restriction of areas
in which any industries, operations or processes or class of industries,
operations or processes shall not be carried out or shall be carried out
subject to certain safeguards. Rule 5 of the Rules framed under the Act known
as Environment (Protection) Rules, 1986 deals with the prohibition and
restriction on the location of industries and carrying on processes and
operations in different area. Sub-rule (2) of Rule 5 says that while
prohibiting or restricting the location of industries and carrying on of
processes or operations in an area, the Central Government shall follow the
procedure laid down in subsequent sub-rules. Sub-rule 3(a) with the procedure
and the manner in which the Central Government can issue notification in the
official gazette. It is an admitted position that on 27.1.1994 the Central
Government, in exercise of its powers conferred by sub-section (1) of clause
(5) of sub-section (2) of section 3 of the Environment (Protection) Act, 1986
read with clause (d) of sub-rule (3) of rule 5 of the Environment (Protection)
Rules, 1986, issued notification SO.60(E) dated 27.1.1994 on environmental
impact assessment of development of projects. The said notification directs
that, on and from the date of publication of the notification in the official
gazette, expansion or modernization of any activity (if pollution load is to
exceed the existing one) or a new project listed in Schedule I of the
Notification shall not be undertaken in any part of India, unless it has been
accorded environmental clearance by the Central Government in accordance with
the procedure laid down in the said Notification. This notification was issued
after inviting objections from the general public. Clause (2) of the
Notification lays down the requirements and the procedure for seeking
environmental clearance of the projects. It is not disputed on behalf of the
respondents that the project in question is a new project and is listed in
Schedule I of the notification. Therefore, the said project, as per the
Notification, cannot be undertaken unless environmental clearance has been
accorded by the Central Government in accordance with the procedure laid down
in the Notification.
26. As and when a project listed in Schedule I is required to be undertaken,
an application is required to be submitted by the project authority to the
Secretary of Environment and Forests, new Delhi and the application has to be
in the proforma as specified in Schedule II of the Notification. The project
authority in this case is the State of Andhra Pradesh. The application is
required to be accompanied with certain documents, viz., (1) a project report,
which inter alia is required to include (ii) Environmental Impact Assessment
Report, (iii) Environmental Management Plan and (iv) details of public hearing
as specified in Schedule IV prepared in accordance with the Guidelines issued
by Central Government and by the Ministry of Forests and Environment from time
to time. Sub-clause (b) of clause (2) says that cases rejected due to
submission of insufficient or inadequate data and plans may be reviewed as and
when submitted with complete data and plans, but the submission of incomplete
data or plans for the second time would itself be sufficient reason for Impact
Assessment Agency to reject the case summarily.
27. As regards hydropower and major irrigation projects and/or their
combination, including flood control, site specific projects are also required
to be included. The project authorities are required to intimate the project
location to the Central Government in the Ministry of Environment and Forests
at the stage of initiating any investigation and survey. Only on receipt of
the intimation, the Central Government in the Ministry of Environment and
Forests is required to convey the decision regarding suitability or otherwise
of the proposed site within a maximum period of thirty days. The site
clearance is valid for a period of five years for commencement of the
construction. At this stage, the communication from the Additional Director,
Ministry of Environment and Forests addressed to the Central Government’s
Standing Counsel becomes relevant and important since the communication states
that the proposal in respect of Pulichintala major irrigation project for site
clearance was received only on 20.10.2004 from the Irrigation and Command Area
Development Department, Government of Andhra Pradesh. It is not the case of
the State Government in any of its counter affidavit or additional affidavit
that site clearance was obtained from the Central Government in the Ministry
of Environment and Forests. It is also not stated that the proposal was
submitted. The present stage as per the material placed on record is the stage
where the project authority, i.e., the State of Andhra Pradesh while
initiating investigation and survey has intimated the project location site to
the Central Government. The Central Government has yet to consider and pass
orders within thirty days. As per the communication of the Additional Director
dated 26.10.2004 the site clearance proposal dated 20.10.2004 is under
examination. From the date of submission of the proposal, a period of thirty
days will be over on or about 19.11.2004. Therefore, the very first
requirement as per the notification dated 27.1.1994 is not yet complied with.
28. Paragraph 3 of the Notification further says that the reports submitted
with the application for environmental clearance shall be evaluated and
assessed by the Impact Assessment Agency and if deemed necessary it will
consult the Committee of Experts. The said committee of Experts will have full
right to entry and inspection of the site at any time prior to, during or
after commencement of the operation of the project. The Impact Assessment
Agency is required to prepare a set of recommendations based on technical
assessment of the documents and data furnished by the project authorities and
supplemented by the data collected through the visits of sites, if undertaken,
and the details of public hearing.
29. Schedule IV refers to the procedure for public hearing and it says that
whosoever applies for environmental clearance shall submit to the State
Pollution Control Board twenty sets of the documents as mentioned in Part I of
the said Schedule. The State Pollution Control Board is required to cause a
notice for environmental public hearing and in the public hearing all persons,
including bona fide residents, environmental groups and others located at the
project site/sites of displacement/sites likely to be affected can
participate. They can also make oral/written suggestions to the State
Pollution Control Board. ‘Person’ has also been explained in Schedule IV and
the procedure envisaged for providing access to the executive summary of the
project to the concerned persons.
30. The assessment by the Central agency is required to be completed within a
period of ninety days from the date of receipt of requisite documents and data
from the project authorities and completion of public hearing and the decision
has to be conveyed within thirty days thereafter. This environmental clearance
granted is also valid for a period of five years from commencement of the
construction or operation of the project. Nowhere in the affidavit of the
State Government it is stated that it has applied for environmental clearance.
No data is furnished; no copy of the application is pointed out. As a matter
of fact, as noticed above, the application is required to accompany
Environmental Impact Assessment Report, Environmental Management Plan and
details of public hearing. Public hearing even as per the stand of the
Government has not yet taken place; it is fixed for 10.11.2004. It is only
when such an application is submitted that it has to be evaluated and assessed
by the Impact Assessment Agency, which thereafter may consult a Committee of
Experts. The constitution of the Committee has to be as follows:
“The Committees will consist of experts in the following disciplines:
(i) Eco-System Management
(ii) Air/Water Pollution Control
(iii) Water Resource Management
(iv) Flora/Fauna Conservation and Management
(v) Land Use Planning
(vi) Social Sciences/Rehabilitation
(vii) Project Appraisal
(viii) Ecology
(ix) Environmental Health
(x) Subject Area Specialists
(xi) Representatives of NGOs/Persons concerned with Environmental Issues.”
The Impact Assessment Agency is, thereafter, required to prepare a set of
recommendations. Assessment has to be completed within a period of ninety days
and thereafter only question of grant of clearance would arise. Even the stage
of assessing the application has not yet arrived.
31. The same paragraph-3 of the Notification says that “no construction work,
preliminary or otherwise, relating to the setting up of the project may be
undertaken till the environmental and/or site clearance was obtained”. As we
have noticed above environmental clearance and site clearance are two
different stages. For site clearance the project authorities are required to
intimate the location of the project while initiating any investigation and
survey and for environmental clearance application as per Schedule II is
required to be submitted along with accompanying documents. Only investigation
and survey can be initiated by the project authorities before site clearance
and before accord of environmental clearance “no other construction work,
whether preliminary or otherwise, can be undertaken” means no work of any
nature relating to the setting up of the project, whether it be construction
work, preliminary or otherwise, can be undertaken. It would include any or
each of the step in the implementation of the project.
32. The case of the State Government is that Pulichintala Project was
conceived in the year 1903 by Mr. Reid, a British Engineer selected the
present site for dam construction. The project initially was intended to be an
irrigation project. The project could not be implemented. During 1951, the
then Madras Government had proposed that Krishna-Pennar Projects be
constructed in stages and for the said purpose Planning Commission appointed
Khosla Committee, which had drawn up an integrated programme in stages. At
Stage III it was proposed to construct dam at Pulichintala across Krishna
river with FRL + 224.5 feet for development of power and for feeding second
crop area in Krishna delta. State Government has pointed out that Pulichintala
Project is now sought to be constructed with reduced FRL + 175 feet for
generation of power and stabilized water supply to Krishna ayacut. The State
Government by taking into consideration the importance of Pulichintala Project
submitted its proposal to the Central Water Commission on 16.1.1996 for its
approval and the Central Water Commission in its 64th meeting of Advisory
Committee on Irrigation and Flood Control and Multipurpose Projects held on
3.4.1996 decided to recommend Pulichintala Project as a techno economically
viable project subject to obtaining environmental clearance. It is further
stated that after recommendation of the Central Water Commission, detailed
investigation and survey was undertaken by the fourth respondent and for
obtaining environmental clearance, as prescribed under the notification dated
27.1.1994. Steps have been taken by the State Government as suggested by the
A.P. Pollution Control Board for conducting public hearing. It was sought to
be conducted on 23.3.1998 but the hearing could not be completed due to
various reasons, including resistance from various groups, political parties
and voluntary organizations.
33. In this background, it is the stand of the State Government that it is
within its right to go ahead with the project and environmental clearance
could be issued at stages also, more particularly when the Central Water
Commission has approved the project, which has also been cleared by the
Planning Commission.
34. The clearance of project by Central Water Commission of Ministry of Water
Resources is not the clearance, which is the subject matter before us.
Clearance by the Central Water Commission is about the technical and
economical aspects. In 1989 guidelines were issued for submission, appraisal
and clearance of irrigation and multipurpose projects before the Central Water
Commission and their acceptance for Planning Commission for the purpose of
inclusion in the State’s development plans. It was resolved in the discussion
in National Conference organized by the Irrigation and Water Resources
Ministry held in July, 1986 that the guidelines indicating the procedure for
submission, appraisal and clearance of irrigation and multipurpose project
should be prepared by the project appraisal organization of Central Water
Commission. The guidelines say that the procedure for submission, appraisal
and clearance outlined in the guidelines shall be followed by the State
Governments, which require that all major irrigation projects and multipurpose
projects shall be investigation in full details and detailed project reports
prepared in accordance with the guidelines issued by the Government of India,
Ministry of Irrigation. The basic planning and hydrological studies relating
to water availability, design flood and sedimentation shall be carried out by
the respective specialized units established in the State Irrigation/Water
Resources Department. These studies shall be vetted by the Central Water
Commission so as to avoid any major change in project features later on. Where
project reports have been examined and cleared by the Central Design
Organization and State Level Appraisal Committees, the examination of project
of CWC will be restricted to Inter State aspects, hydrology and dam safety,
water availability, water accounting and economic viability. States are
required to submit ten copies along with two sets of detailed project reports
along with the letter of clearance by the Central Design Organization and
State Level Appraisal Committees. Clause 2.22 of the guidelines provided that
the Central Water Commission will send copies of the project reports and
relevant proforma to the Ministry of Environment and Forests for obtaining
clearance from the environment and forest angle.
35. Even the National Conference held in 1986 had made it clear that the
projects should not be sent to the Centre for techno-economic examination
unless these have been thoroughly and comprehensively prepared on an
integrated basis by a multidisciplinary cell in conformity with the guidelines
laid down for the purpose and the Central Agencies in turn should review the
procedures for techno-economic and other scrutinizes in consultation with the
States and Union Territories.
36. Needless to add that as per the State Government’s stand, the Advisory
Committee on Irrigation and Flood Control had only decided to “recommend” that
Pulichintala Project was a techno-economically viable project. Whether on such
recommendation any clearance was or was not ultimately accorded by the Central
Water Commission is not stated in the counter affidavit. However, we are not
concerned with the clearance by the Central Water Commission, but are
concerned, as noticed above, with the environmental clearance, which as per
the decision of the Supreme Court is absolutely necessary before State of
Andhra Pradesh can undertake the project in question. We have already referred
to the letter from the Additional Director, Ministry of Environment and
Forests, Government of India dated 26.10.2004. It is a communication to the
Central Government’s Standing Counsel requesting to bring to the notice of the
Court that even site clearance has not yet been granted and a request for that
purpose was received from the State Government only on 20.10.2004 and still
there are thirty days from the date of receipt of the request for giving site
clearance.
37. As per the procedure laid down in the notification dated 27.1.1994 for
obtaining environmental clearance of any project, twenty sets of documents are
required to be submitted to the concerned Sate Pollution Control Board. Though
no details have been submitted before us by the State Government when it
initiated the process of seeking environmental clearance, but what can be
noticed by us and what may be presumably by us from the facts on record is
that the State Government must have initiated steps for environmental
clearance prior to 23.3.1998, since it is stated that as per the suggestion of
the A.P. Pollution Control Board steps were taken for conducting public
hearing on 23.3.1998. Application for environmental clearance of the Project
with twenty sets of documents, as referred to in Schedule IV, when presented
to the State Pollution Control Board would require the State Pollution Control
Board to take steps for issuing notice of public hearing and the result of
public hearing has to be incorporated in the formal application, which
ultimately will have to be submitted to the Secretary, Ministry of Environment
and Forests, New Delhi in Schedule II. Such an application is also required to
be accompanied by a project report, which shall inter alia include an
Environmental Impact Assessment Report and Environmental Management Plan and
of course details of public hearing prepared in accordance with the guidelines
issued by the Central Government. Nowhere it is stated that any Environmental
Impact Assessment Report has or has not been obtained or whether any
Environmental Management Plan has been prepared. The entire affidavit of the
State Government is silent on this aspect and gives an impression that these
steps are yet to be taken and all necessary formalities is yet to be complied
with of submitting appropriate application in proforma specified in Schedule
II of the Notification dated 27.11.1994. It is only thereafter that the case
will have to be assessed and examined by the Central Agency. As noticed above,
any application, if submitted with insufficient or inadequate data and plans
is liable to be rejected and can only be reviewed when submitted with complete
data and plans and submission of incomplete data and plans for the second time
itself is sufficient for Impact Assessment Agency to reject the case
summarily. Considering the mandatory nature of the environmental clearance,
procedure has to be meticulously followed. Only on environmental clearance any
construction, preliminary or otherwise, relating to setting up of the project
can be undertaken. There is an express prohibition that “no construction work,
preliminary or otherwise, relating to the setting up of the project may be
undertaken till the environmental and/or site clearance is obtained”.
38. We under stand the anxiety of the State Government in speedy
implementation of the project for which the State Government might be
committed. But the question before us is that can the State Government be
permitted to flout the directions of the Supreme Court or the laws made by the
Parliament. The answer has to be in the negative that it cannot do so. In the
suit filed by the State Government against the State of Karnataka itself this
position was clarified that under Article 256 of the Constitution it is an
obligation on the part of the State to exercise their power ensuring
compliance with laws made by the Parliament. The Supreme Court specifically
asserted that several provisions of the Constitution have been tested in the
last fifty years and there is no reason to conceive that any State will
proceed ahead with its object without getting sanction/concurrence of the
appropriate authorities and without compliance with the relevant statutes or
laws. Only after proper scanning and approval by the Central Government –
Ministry of Environment and Forests, the State Government would be entitled to
carry out and implement the proposed project.
39. There is no manner of doubt that no development is possible without some
adverse effect on ecology and environment and the projects of public utility
cannot be abandoned. It is always necessary to adjust the interests of the
people as well as to maintain environment; balance has to be struck between
two interests. Where the commercial venture or enterprise would bring in
results, which are far more useful for the people, difficulties of a small
number of people have to be bypassed. The comparative hardship has to be
balanced and the convenience sand benefit to the larger section of the project
has to get primacy over comparably lesser hardship. Sustainable development is
essentially a policy and strategy for continued economic and social
development without detriment to the environment and natural resources on the
quality of which continued activity and further development depend. In T.N.
Godavarman Thirumalpad v. Union of India ((2002) 10 SCC 606), it was held that
duty is cast upon the Government under Article 21 of the Constitution to
protect the environment and there are two principles governing law of
environment, viz., the principle of sustainable development and precautionary
principle. We are equally conscious of the principle that Courts in exercise
of their jurisdiction will not transgress into the field of policy decision
and would also not interject the implementation of the project as per the
policy of the Government, but for the time being the second limb of the writ
petition that whether or not the project should continue at the present site
or not is premature as was held by Division Bench of this Court in earlier
Writ Petition No.15425 of 2001. Site clearance and environmental clearance by
the Central Government alone will enable the State Government to proceed ahead
with the project. Both the stages of site clearance and environmental
clearance are not yet over. It is a settled principle that when an authority
has power to accord permission or grant clearance, such power to grant
permission or to accord sanction also includes therein the power not to grant
such permission or accord such sanction. It cannot be presumed today that the
State Government will necessarily get site clearance; it cannot also be
presumed that the State Government will necessarily get environmental
clearance. Therefore, till such clearances are granted, the challenge by the
petitioners to the project on the other grounds is premature and need not be
gone into by us.
40. We have already noticed that only the question being considered is whether
or not there should be a stay. We are not considering such question of grant
or non-grant of stay in a matter where already the project stands cleared and
the persons likely to be adversely affected have approached the Court for
staying implementation of the project. Only in a situation like the later that
the question of balance of convenience, comparative hardship would arise for
consideration. May be that on such consideration the Court might be persuaded
not to grant stay in larger public interest at the behest of a minority
section of the population. But it is a case like the present one where as per
the admission of the State Government, there is neither any site clearance
granted nor environmental clearance obtained and public hearing is yet to take
place, such consideration may not be relevant at all. It is only when public
hearing is concluded that the State Government will be entitled to apply for
environmental clearance. On the ratio of the decision of the Supreme Court
rendered in a suit filed by the Andhra Pradesh Government against the State of
Karnataka, it is not at all permissible for the State Government to proceed
ahead with the project. In its over-anxiety, to complete the project
expeditiously in a hurled manner, the State Government floated tenders and
awarded contract also. The contractor has undertaken the work and
justification that is being projected in the reply is that the work undertaken
is only an investigation work for assessing soil parameters for the purpose of
preparing and finalization of designs, drawings, etc. Comprehensive design for
a plan is required to be submitted before obtaining approval from the Central
Water Commission. The stand which the State Government has taken in
paragraph-7 of the counter affidavit dated 26.10.2004 itself would suggest
that it is more than an investigation work, which is going on. It is stated in
the said paragraph that site is suitable in all respects and construction of
dam always involves submergence and even if the project is implemented there
will not be any major impact. The notification envisages that no work
whatsoever, whether preliminary or otherwise, can be undertaken. A distinction
was tried to be drawn between construction work and any other work and it was
pointed out that digging would not come within the definition of construction.
The digging was only for the purpose of soil testing and for the purpose of
preparation of designs. At the stage of initiating any investigation and
survey that project authorities are required to intimate the location of the
site to the Central Government so as to grant site clearance; even that stage
is not over. Therefore, any work undertaken on the spot would not be
permissible under the notification.
42. On behalf of the respondents, it was urged that the guidelines and the
notification dated 27.1.1994 issued by the Central Government are not having
any statutory force. The same can be taken to be merely in the nature of
executive instructions for the guidance of the persons applying for
environmental clearance. Same have no binding effect and even if there is some
infraction on the part of the State Government a writ petition will not lie
seeking enforcement of the procedure laid down in the notification. Reliance
was placed on the decision of the Supreme Court in J.R. Rathupathy v. State of
A.P. ((1988) 4 SCC 364). We have given due consideration to the submission
made but do not find any force in such submission. We have already observed
above that it is not the case of the State Government that it is not bound by
the Notification of 1994. We have also taken note of the fact that the State
Government was a party to the suit before the Supreme Court in which itself it
was held that the Government is bound to comply with the procedural laws
before undertaking any project. Therefore, the objection raised on behalf of
the other respondents, who are only beneficiaries, will have no force and they
cannot be permitted to urge what cannot be urged by the State Government.
43. Respondents also placed reliance upon the decision of the Bombay High
Court in Goa Foundation v. Konkan Railway Corporation (AIR 1992 Bombay 471)
urging that the Division Bench in the said case dismissed the writ petition
filed as public interest litigation and declined to exercise writ jurisdiction
holding that such a petition filed as public interest litigation cannot be
entertained since the writ jurisdiction is to advance the cause of justice and
not to defeat the exercises undertaken by the Government for the public
benefit. The machinery of the Court should not be used for subserving the
interest of few individuals or interest of a local area to the detriment of
the public at large. It was urged in the said case before the Bombay High
Court that laying of new broad gauge railway line was sought to be prevented
by filing a writ petition and it was sought to be got stayed on the ground
that there was no environmental clearance obtained. The writ petition was
dismissed on the ground that environmental clearance was not necessary and
even if environmental clearance is not obtained, there is no question of grant
of stay.
44. Reliance placed on behalf of the respondents on the aforementioned
decision of the Bombay High Court is totally misplaced. The learned Judges of
the Bombay High Court took notice of the respective stand of the parties. In
the said case, the claim of the writ petitioner was that the alignment of rail
track would have devastating and irreversible impact upon some lands and that
undertaking such activity without obtaining environmental clearance was not
permissible. On the second question, the Division Bench held that the
provisions of the Environment (Protection) Act had no application in respect
of the work undertaken in exercise of powers under Section 11 of the Railways
Act. It was held that the non-obstante clause of Section 11 makes it clear
that the provisions of the Environment (Protection) Act do not bind the
construction or maintenance of railway line. Irrespective of that objection
the Court took into consideration an aspect that it was not open to frustrate
the project of public importance to safeguard the interest of few persons and
therefore there was no balance of convenience in favour of the writ
petitioners. Balance has to be struck between two interests and the Courts are
bound to take into consideration the comparative hardship, which people in the
region would suffer by stalling the project of great public utility since the
cost of project was likely to escalate from day to day.
45. In the case in hand such is not the situation. The provisions of the
Environment (Protection) Act are applicable and it is impermissible for the
State to proceed ahead or undertake the construction for the project without
obtaining environmental clearance. Whether undertaking such a project is for
the benefit of a particular section of the society or not or is in larger
public interest is not the consideration before us at this stage. Without
deciding this question we proceed on the assumption that the construction of
project is in larger public interest of immense benefit to the major
population of the State Andhra Pradesh, and is of an extreme importance having
considerable impact and the anxiety of the State Government is to complete the
project as quickly as possible. But can the State Government be permitted to
flout the mandatory provisions of law when the Supreme Court in the suit filed
by the State Government categorically held that implementation of the project
cannot be undertaken without prior concurrence/clearance. It was urged on
behalf of the respondents with considerable data that a larger number of
projects have already been undertaken by the State Government and in most of
the cases environmental clearance has not yet been obtained. Even there is no
clearance from the Planning Commission or from the Central Water Commission
but works on such projects are in progress. Thus, it was urged that since a
number of other projects are continuing in the State and works are in progress
on those projects, there will be no lawful justification in staying the
implementation of the project in this case since post-facto clearance can
always be obtained by the State Government.
46. From the nature and the contents of the affidavit in reply filed by the
State Government, it also appears that the State Government is labouring under
the impression that it will be permissible for it to obtain environmental
clearance post-facto and public hearing is only a formality and, therefore,
there should not be any interjection of the project of such a great magnitude
of great public importance, which so dear to the State Government. Again such
a stand has to be turned down and deprecated that when law requires a thing to
be in a particular manner, the same must be done in the same manner or not
done at all. The law envisages that no construction, preliminary or otherwise,
can be undertaken without environmental clearance and the judgment of the
Supreme Court also holds that it is impermissible to undertake construction of
project before such a clearance, therefore, there is no reason why prayer made
by the petitioners to that extent in the writ petition be not allowed.
47. In Narmada Bachao Andolan case (5 supra) environmental clearance had
already been given much prior to coming into force of 1994 Notification. Such
notification was issued during the pendency of one of the writ petitions. The
petitioners were anti dam organizations and were opposing the construction by
raising the height of the dam, which had been in existence since 1986. They
had chosen to challenge the clearance given in 1987 by filing writ petition in
1994. It was noticed that the project, in fact, had already been cleared more
than twenty five years ago when foundation stone was laid by late Pandit
Jawaharlal Nehru and thereafter there had been agreements in 1974 between four
Chief Ministers of Madhya Pradesh, Gujarat, Maharashtra and Rajasthan for
undertaking of the project. Dispute had arisen with regard to the height of
the dam, which was settled with the award given in 1978. In the meanwhile,
environmental studies had been conducted. The Government finally gave
environmental clearance in 1987. Thereafter construction of the dam was
undertaken and hundreds and crores were spent thereupon where after writ
petitioners chose to file the writ petition. In that background, the Supreme
Court held that when projects are undertaken and hundreds and crores of public
money are spent, individuals and organizations under the garb of public
interest litigation cannot be permitted to challenge the decision taken after
a lapse of considerable time. In paragraph 231 of the judgment, it was
observed that while exercising jurisdiction in public interest litigation
cases, the Court has not forsaken its duty as a Court of law dispensing
justice in accordance with law. It is only where there has been a failure on
the part of any authority in acting according to law or in non-action or
acting in violation of the law that courts have stepped in.
48. In view of what has been discussed above holding that action of the State
Government in implementation of the project without obtaining environmental
clearance as envisaged under the provisions of the Environment (Protection)
Act, 1986, the rules framed thereunder and the notification, is illegal and
arbitrary, it is not permissible for the State Government to proceed ahead
with the implementation of the said project till such clearances are obtained.
We dispose of this writ petition with direction to the State Government not to
proceed ahead in implementation of the project and not to undertake any
construction work, whether preliminary or otherwise, till environmental
clearance is obtained. The writ petition to that extent is allowed. The
miscellaneous applications are also ordered. The writ petition for the other
reliefs is disposed of with the observation that the said reliefs, at this
stage, are premature.